Story "dragging"

Problem
A feature isn't necessarily implemented 100% in one sprint (e.g. because it's still in QA and thus, not yet "done"). So if e.g. 90% of the work for one feature has been done in one sprint, it is not reflected in the burndown chart, since the respective feature is still not set to "done".
Discussion
Stories "dragging" through means they are too large for a single sprint, and should be decomposed further. Counting partial points, or re-estimating afterwards would only hide that issue, hurting the team long term.

So if your team targets 40 points each sprint, and the 8 point story is NOT completed this sprint, the team only delivers 32 points. But next sprint this large story will be completed quickly, allowing the team to actually meet their 40 point commitment, AND pull another story into the sprint delivering ~48 points. The average of the two sprints is still 40, and the velocity remains true.